RAIL SYSTEM EXPERIENCES OF MESCIOGLU ENGINEERING IN LAST FIVE YEARS
1. Ankara – Istanbul High Speed Railway Project
1.1. Sincan – Esenkent Section, Design and Construction Supervision and Consultancy Services
--Controlling, Engineering, Supervision and Consultancy Services of all projects of 15,50 kilometers long double-track high speed railway.
--Engineering and Consultancy Services Earthworks; 2.570.000 m3 cut, 1.375.000 m3 fill
--Engineering and Consultancy Services of 360 meters viaduct, a railway bridge, 3 bridges, 15 culverts, 2 vehicle overpasses, 10 vehicle underpasses and 280 meters long tunnel (NATM).
--Determining, preparing and controlling of the progress payment.
Contractor
Cost of Construction
Administration
: SIGMA Construction Company
: 19.000.000 - EURO
: General Directorate of Turkish Railways (TCDD)
1.2. Ankara (Esenkent) – Eskişehir Section, Design and Construction Supervision and Consultancy Services
--Controlling, Engineering, Supervision and Consultancy Services of all projects of 200 kilometers long double-track high speed railway.
--Engineering and Consultancy Services Earthworks; 14.240.000 m3 cut, 10.850.000 m3 fill
--Engineering and Consultancy Services of 3996 meters viaduct, 2 motorway bridges, 17 bridges, 254 culverts, 27 overpasses, 33 underpasses and 471 meters long tunnel (NATM).
--Determining, preparing and controlling of the progress payment.
Contractor
Cost of Construction
Administration
: OHL (SPAIN) – ALARKO Joint Venture
: 650.000.000 - EURO
: General Directorate of Turkish Railways (TCDD)
1.3. Eskişehir – Inönü Section, Design and Construction Supervision and Consultancy Services
--Controlling, Engineering, Supervision and Consultancy Services of all projects of 22 kilometers long double-track high speed railway.
--Engineering and Consultancy Services Earthworks; 1.476.000 m3 cut, 1.400.000 m3 fill
--Engineering and Consultancy Services of 4 vehicle underpasses, 2 vehicle overpasses and drainage systems.
--Determining, preparing and controlling of the progress payment.
Contractor
Cost of Construction
Administration
: SIGMA Construction Company
: 23.000.000 - EURO
: General Directorate of Turkish Railways (TCDD)
2. Adana Light Rail Transit System Supervision and Consultancy Services
Adana Light Rail Transit System Project is 14 kilometers long mass transit project, having two major parts as Civil Works and Electromechanical System Works.
2.1. Civil Works
- Depot Area having the Workshop, Administrative Building, Auxiliary Power building, Auxiliary Building, Vehicle Washing Unit and necessary places for the parking of vehicles.
- Railway line of 13.460 meters long, Structural Composition:
3.200 meters cut&cover tunnel,
1.550 meters retained cut,
970 meters retained fill,
4.700 meters R.C viaduct,
225 meters steel viaduct,
2.200 meters at-grade line.
- 13 stations on the railway line, having a total length of 1.100 meters. The structural compositions:
- Additional 380 meters cut&cover railway structure at the entrance of the Depot Area
2.2. Electromechanical System Works
- 36 vehicles.
- Power Supply and Distribution:
Traction power substations,
Station power substations,
Depot area and workshop’s electrical equipment.
- Lighting and Sockets for stations, depot area and Workshop.
- Overhead Line System:
Main line and depot area.
- Workshop Equipment
- Communication, Control and Signalization Systems:
Fiber Optic,
Radio,
Public Address,
Telephone,
Closed Circuit TV (CCTV),
Clock, Fire Alarm,
Signalization,
Scada and Fair Collection Systems.
Contractor
Cost of Construction
Administration
: ALARKO (Civil), ABB-Adtranz-Bombardier (Electromechanical)
: 260.000.000 - EURO
: Adana Metropolitan Municipality
3. Extension of Existing Konya Tram Line Preliminary Project, Feasibility Study and Design of Application
Feasibility study of 5 kilometers long double-track light rail transit system has been prepared efficiently and it has been approved by DLH (General Directorate of Construction of Railways, Ports and Airports) approval authority. Application projects have been completed appropriately according to the approved feasibility study. Also, 8 stations and a warehouse project have been designed.
4. Management and Optimization of Railway Maintenance and Renewal Activities with Geomedia and Research
In MR.GIS solution, in the context of effective and efficient railway transportation, it is intended to create an information based system for track maintenance and renewal (M&R) services. It is possible to build degradation model track geometry by using condition based methods on the base of data gathered on the track. It is possible to prepare maintenance and renewal programs in short and long term by using the degradation model of the track geometry.
Geographical information systems (GIS) can be used to combine geographical and non-geographical data together and GIS enables the users to follow M&R programs on a visual environment.
With MR.GIS, you can manage records of;
- Existing conditional information on railway track layout and engineering structures (including construction information)
- History of Maintenance and Renewal works
- Operational Information
- Measurements
And also with these information;
- Degradation model of track geometry
- M&R planning
- Optimization of resources
- Querying and Reporting
can be performed
MR.GIS solution has been accepted as national advantage by TUBITAK and taken into support context. In addition to presenting a beneficial to our country with our studies, because of being GIS based, our project which is first over the world showed that both our country and our technology has been improved and our competency on railway realized.
References
HIGHWAY DESIGN PROJECTS
977
km
APPLICATION PROJECTS
155.4
km
APPLICATION PROJECTS STRUCTURE
11.260,41
m2
PENDIK MUNICIPALITY APPLICATION PROJECTS
1000
m2
TUNNEL PROJECTS
2903
m.
BRIDGE PROJECTS
45106,11
m2
RAILWAY DESIGN PROJECTS
221
km
SEWERAGE SYSTEM DESIGN WORKS
649.275
m.
WASTE WATER TREATMENT PLANT PROJECT
1
Unit
POTABLE WATER TREATMENT PLANT PROJECT
1
Unit
ASKİ CONSULTANCY SERVICES
All infrastructure projects
between 2002-2003
FAST TRAIN RAILWAY CONSULTANCY SERVICES
270
km
ADANA METROPOLITAN MUNICIPALITY SUBWAY CONSULTANCY SERVICES
Ankara (Esenkent) - Eskisehir High Speed Railway Section
Design and Construction Supervision and Consultancy Services
Contractor:
OHL (SPAIN) - ALARKO Joint Venture
Cost of Construction:
650.000.000 - EURO
Administration:
Genaral Directorate of Turkish Railways (TCDD)
Total Km:
206 km
Scope of The Project:
•
Controlling, Supervision and Consultancy Services of Design Projects,
•
Controlling and Consultancy of Earthworks: 14.240.000 m3 cut, 10.850.000 m3 fill,
•
Construction and Design Consultancy of 3993 m Viaduct,
2 Motorway Bridges, 17 River Bridges, 254 Culverts,
26 Overpasses, 30 Underpasses and a 471 m Long Tunnel,
•
Determining, Preparing and Controlling of The Progress Payment.
Sincan - Esenkent High Speed Railway Section
Construction Supervision and Consultancy Services
Contractor:
SIGMA Construction Company
Cost of Construction:
19.000.000 - EURO
Administration:
Genaral Directorate of Turkish Railways (TCDD)
Total Km:
15.50 km
Scope of The Project:
•
Controlling and Consultancy of Earthworks: 2.570.000 m3 cut, 1.375.000 m3 fill,
•
Construction Consultancy of a 360 m Long Viaduct, 1 Railway and 3 River Bridges, 15 Culverts, 2 Overpasses, 10 Underpasses and a 280 m Long Tunnel (NATM),
•
Determining, Preparing and Controlling of The Progress Payment.
Eskisehir - Inonu High Speed Railway Section
Construction Supervision and Consultancy Services
Contractor:
SIGMA Construction Company
Cost of Construction:
23.000.000 - EURO
Administration:
Genaral Directorate of Turkish Railways (TCDD)
Total Km:
26 km
Scope of The Project:
•
Controlling and Consultancy of Earthworks: 1.476.000 m3 cut, 1.400.000 m3 fill,
•
Construction Consultancy of 5 Overpasses, 4 Underpasses and Dranaige Systems,
•
Determining, Preparing and Controlling of The Progress Payment.
Adana Light Rail and Metro Transit System
Supervision and Consultancy Services
Controlling and Consultancy of Following Civil Works;
-
Depot Area Having a Workshop, Administrative Building, Auxilliary Power Building, Auxilliary Building, Vehicle Washing Unit,
-
3.200 m Cut and Cover Tunnel,
-
1.550 m Retained Cut,
-
970 m Retained Fill,
-
4.700 m R.C. Viaduct,
-
225 m Steel Viaduct,
-
2200 m at-grade line,
-
13 Stations,
-
Additional 380 m Cut and Cover Railway Structure at The Depot Area.
•
Controlling and Consultancy of Following Electromechanical System Works;
-
36 Vehicles,
-
Power Supply and Distribution,
- Traction Power Substations
- Station Power Substations
- Depot Area and Workshop's Electrical Equipment.
-
Lighting and Sockets for Stations, Depot Area and Workshop,
-
Main Line and Depot Area Overhead Line System,
-
Workshop Equipment,
-
Communication, Control and Signalization Systems.
Extention of Existing Konya Tram Line Preliminary Project
Feasibility Study and Design of Application
Contractor:
-
Cost of Construction:
-
Administration:
Konya Metropolitan Municipality
Total Km:
5 km
Scope of The Project:
•
Feasibility study of 5 km of long double - track light rail transit system, which was approved by DLH (General Directorate of Construction of Railways, Ports and Airports), has been prepared,
•
Application projects have been prepared according to the approved feasibility study,
•
8 stations and a warehouse project have been designed.
Bill of Quantities as an Attachment of Tender Documents.
Bridges, Interchanges and Roads Detailed Design Projects in European Side (30. Stage) (ISTANBUL)
Contractor:
-
Cost of Construction:
-
Administration:
The Great Municipality in Istanbul
Total Km:
-
Scope of The Project:
The project consists of totally 35 junction design, over 250 km. preliminary design and route study. Finally 25 detailed design projects has been completed. More than 20 junctions traffic count, analyze and investigation has been established. For designing and evaluating 157 km road, geotechnical, topographical site surveys and expropriation of necessary are as have been performed.
Analyzing, Counting and Simulating of More Than 20 Junction and Crossing Points.
Pendik Kaynarca Neighborhood Under E-5 Underpass with Bazaar Project
Contractor:
-
Cost of Construction:
1,781,000 TL
Administration:
Pendik Municipality
Total Km:
-
Scope of The Project:
Design of underpass with stores for pedestrians in Pendik in Istanbul. This pedestrian underpass is a shopping center with 22 stores.
This project involves electrical, mechanical, architectural and static design and projects.
Underpass has a dimension of 57m length, 18m wideness and totally 1308 square meters closed area.
INFRASTRUCTURE PROJECTS
SEWERAGE PROJECTS
Work
Administration
Contractor
Total
Year
Karaman
İller Bankası
Eryapı Ltd.Şti.
649.275 Km
2000-2001
SEWETAGE TREATMENT PLANT PROJECT
Work
Administration
Contractor
Total
Year
Çelikhan (Adıyaman)
Başbakanlık Güneydoğu Anadolu Projesi Bölge Kalkınma İdaresi Başkanlığı
Kaya Müh. Ltd. Şti.
1 Unit
1996-1999
FRESH WATER TREATMENT PLANT PROJECT
Work
Administration
Contractor
Total
Year
Küçükkuyu (Çanakkale)
İller Bankası Gen. Müd.
Kaya Müh. Ltd. Şti.
1 Unit
1998-2001
FEASIBILITY REPORT PREPARATION
Work
Administration
Contractor
Year
Samsun-Terme Kocaman Grubu (Miliç Irmağı ve Kolları) Taşkın ve Rüsubat Kontrolü Fizibilite Raporu Hazırlanması Hizmet Alımı İşi
Dsi VII. Bölge Müdürlüğü Samsun
DSİ VII. Bölge Müdürlüğü Samsun
2007------
SURVEYING
Kayseri Cadestre Mapping
Details of The Project:
Job includes 7800 parcels and surrounding areas, inbuilt cadastre plots and/or Map information digitizing, renewing cadastral parcel productivity. GPS and Total Station equipment are used to in the application and preparation of land register sheets.
Konya Cadestre Mapping
Details of The Project:
Job includes 28400 parcels and surrounding areas, inbuilt cadastre plots and/or Map information digitizing, renewing cadastral parcel productivity. GPS and Total Station equipment are used to in the application and preparation of land register sheets.
Düzce Cadestre Mapping
Details of The Project:
Job includes 8000 parcels and surrounding areas, inbuilt cadastre plots and/or Map information digitizing, renewing cadastral parcel productivity. GPS and Total Station equipment are used to in the application and preparation of land register sheets.
PHOTOGRAMMETRY
Kulu Digital Photogrammetry Map Production
Details of The Project:
Digital photogrammetric Map collection of a 217 km long road corridor Flight has been done using a Zeiss RMK Top30 Camera. With a long orthophoto maps has been used to come up with solutions.
Kahramanmaraş Digital Photogrammetry Map Production
Details of The Project:
A total area of 27000 Ha which are in places residential sections and which are going to be mapped with a scale of 1/1000 and 1/5000,produced as Digital Photogrammetric Maps and Ortho-Photos. Kahramanmaraş Municipality, is using this data for every project as infrastructure (zoning ordinance, transportation plans, urban information system, water and waste water planning, cadastre). Flight has been done using the Zeiss RMK Top30 Camera of which we are the only Authorized Distributor in Turkey
Antalya Digital Photogrammetry Map Production
Details of The Project:
Within the City Municipality borders, with an area of 102000 Ha has been a project issued for us as a 1/1000 and 1/5000 scale digital photogrammetric map and orthophoto production. The City Municipality has done all its investments in infrastructure (Tourism, Transportation, Zoning Ordinance, Urban Information System, etc.). Flight has been done with the Zeiss RMK Top30 Camera which we are the only Authorized Distributor in Turkey.
Bursa Digital Photogrammetry Map Production
Details of The Project:
The borders includes the City Municipality and near residential areas with a total area of 35000 Ha 1/1000 and 1/5000 digital photogrammetric maps and orthophoto production has been a project issued to us. The City Municipality has done all its investments in infrastructure (Tourism, Transportation, Zoning Ordinance, Urban Information System, etc.). The flight has been done using a Vexcel XP Large Format Digital Camera.
CONSULTANCY SERVICES
1 - CONSULTANCY SERVICES for ASKİ
Consultancy Services for all infrastructural projects of The Great Municipality of Ankara; General Directorate of ASKİ with construction cost of 552.538.286.052-TL (2002/1 unit price). Details are below:
Akpınar, Karapınar, Gökkuşağı ve Cevizlidere Mah. PS / YS İnşaatı
Kent İnşaat
05.09.2002
2 - CONSULTANCY SERVICES for TCDD
WORK
ADMINISTRATION
CONTRACTOR
TOTAL
Ankara-Esenkent-Eskişehir Demiryolu Hızlı Tren Proje ve Yapım Hizmeti işi
TCDD
Alarko OHL İspanya Ortak Girişimi
222 Km.
Ankara-İstanbul Hızlı Tren Projesi Esenkent-Sincan Arası Kontrollük ve Danışmanlık Hizmetleri
TCDD
SİGMA İNŞAT
48 Km
3 – CONSULTANCY SERVICES for THE GREAT MUNICIPALITY OF ADANA
WORK
ADMINISTRATION
CONTRACTOR
TOTAL
Adana Raylı Taşıma Sistemi, Kontrollük ve Müşavirlik Hizmet Alımı işi
Adana B.Şehir Belediyesi
Bombardiyar Transportation Alarko ABB Elektrik Konsorsiyum
13 Km.
4 - CONSULTANCY SERVICES for BOTAŞ
WORK
ADMINISTRATION
CONTRACTOR
TOTAL
YEAR
İç Tesisat Doğalgaz Dönüşüm Projesi
Botaş Boru Hatları ile Petrol Taşıma A.Ş.
Simge Tekstil San.
Ltd. Şti.
1 Unit
2003-2003
İç Tesisat Doğalgaz Dönüşüm Projesi
Botaş Boru Hatları ile Petrol Taşıma A.Ş.
Bayramlar Dokuma San. ve Tic. A.Ş.
1 Unit
2003-2003
İç Tesisat Doğalgaz Dönüşüm Projesi
Botaş Boru Hatları ile Petrol Taşıma A.Ş.
Kotonteks Tekstil ve Gıda Ürünleri San ve Tic. A.Ş.
1 Unit
2003-2003
Tuz Gölü Yeraltı Doğal Gaz Depolama Projesi, Su Temin, Tuzlu Su Boşaltım Ve Doğal Gaz Boru Hatları İle Enerji Nakil Hatları Etüt, Harita ve Kamulaştırma Planları Müşavirlik Hizmetleri